Right-to-left schedule from a real BOM (HADES flight controller, 67 parts). Top 16 by urgency. As of 2026-06-26: 8 parts LATE, 3 must act now. Critical path: LD39200PU33R (18wk).
TODAY 2026-06-26
LD39200PU33Rsensor_ic - 18wk
W25N01GVZEIG TRsensor_ic - 18wk
MPRLS0025PA00001Asensor_ic - 18wk
IIS2MDCTRsensor_ic - 18wk
MIC26903YJL-TRregulator_ic - 14wk
INA219AIDCNRregulator_ic - 14wk
PCA9685PW,118regulator_ic - 14wk
53048-0210connector - 10wk
53048-0710connector - 10wk
ABM8G-25.000MHZ-4Y-Tcrystal - 10wk
HTSW-108-07-T-Tconnector - 10wk
53048-0610connector - 10wk
2026-06-022026-12-08