Sourcing Timeline — 500-unit build, target 2026-12-01

Right-to-left schedule from a real BOM (HADES flight controller, 67 parts). Top 16 by urgency. As of 2026-06-26: 8 parts LATE, 3 must act now. Critical path: LD39200PU33R (18wk).

specRFQawardPOlead timereceive
TODAY 2026-06-26
LD39200PU33Rsensor_ic - 18wk
LATE
W25N01GVZEIG TRsensor_ic - 18wk
LATE
BMI088sensor_ic - 18wk
LATE
MPRLS0025PA00001Asensor_ic - 18wk
LATE
IIS2MDCTRsensor_ic - 18wk
LATE
MAX-8Qsensor_ic - 18wk
LATE
STM32H753VIT6mcu - 16wk
LATE
STM32F405RGT6mcu - 16wk
LATE
MIC26903YJL-TRregulator_ic - 14wk
ACT NOW
INA219AIDCNRregulator_ic - 14wk
ACT NOW
PCA9685PW,118regulator_ic - 14wk
ACT NOW
53048-0210connector - 10wk
SOON
53048-0710connector - 10wk
SOON
ABM8G-25.000MHZ-4Y-Tcrystal - 10wk
SOON
HTSW-108-07-T-Tconnector - 10wk
SOON
53048-0610connector - 10wk
SOON
2026-06-022026-12-08